Project overview
Harlin Technical Services is completing audio remediation, rigging, acoustical treatment, networking, commissioning, and closeout work across the BGHS Arena, Performing Arts Center, Football Stadium, and Soccer Field.
- Client: Bowling Green Independent School District
- Project status: Active
- Client-required completion target: August 5, 2026
- HTS project lead: Barlow Harlin
- Last portal update: July 23, 2026
Current status by venue
Performing Arts Center
- Both Danley SH-96 loudspeakers are installed, secured, wired, terminated, and tested.
- Both TH-115 subwoofers have been corrected to the intended orientation and support arrangement.
- Final system measurement and tuning are complete.
- Remaining work is limited to minor finish items, final acceptance, and closeout documentation.
IMG_2369.MOV
Arena
- The loudspeaker system is installed and substantially complete.